Haiti - Economy : LNG Gas terminal, work will resume soon - HaitiLibre.com : Haiti news 7/7
 New revised electoral calendar (Oct. 28, 2026)





iciHaiti - International Expos : Training on the preparation, organization, and management of Haitian pavilions

2026-2027 Nations League : 3 key Grenadiers out for the quarter-finals

iciHaiti - FLASH : 2026-27 D1 Opening Series : Matchday 2 Schedule

iciHaïti - Formation : Launch of training in entrepreneurship

Dominican Republic : Strengthening of military patrols at the border


more news


Haiti - Leisure : Did you know ? #75

Haiti - News : Zapping...

Haiti - Economy : Agreement signed between Cap-Haitien and Canada

Haiti - Politic : Kenscoff looks toward the future once again (video address by the Prime Minister)

Haiti - FLASH : Helicopters from El Salvador fire rockets at the residence and headquarters of «Lanmò San Jou» (video)


more news


Haiti - Economy : LNG Gas terminal, work will resume soon


Haiti - Economy : LNG Gas terminal, work will resume soon

Officially launched Tuesday, August 20, 2013, by the Prime Minister, Laurent Lamothe, the construction of the supply dock and storage of liquefied natural gas (LNG), near Titanyen, have made little progress...

Reynold Bonnefil, the Director General of the Haytrac Power & Gas S.A. (HPG) explained that during the preliminary work all authorizations had not been received and it is only early December that the Haitian administration has issued all documents of exemption for HPG and its foreign partners (ANDINAT, PROMIGAZ and GASENER). He asserts that despite this delay "The port will be ready by mid-2015 as expected [...]" and announced the resumption of work by two or three weeks stressing "We have already ordered trucks and tanks which should enter the country by the end of January to begin work on the shuttle between the Dominican Republic and Haiti [...] from March we will start to receive the first deliveries of natural gas [...]"

Recall that this project of the Haytrac Power and Gas S.A. and its partners will cost $123 million and will be completed in the next 36 months, it will create 159 direct jobs qualified and about 6,000 indirect jobs. The construction of the terminal, with an area of ​​75,000 m2 will significantly reduce environmental pollution, the use of charcoal and wi drop up to 28% the cost of gasoline in the local market.

The project will be implemented in two phases :

Phase I The construction of a storage terminal of 15,000 m3 fopr the importation of liquefied natural gas at the level of Cité Soleil and Morne à Cabrit, capacity that will be doubled later.

Phase II Construction of a pipeline to supply the industrial area of ​​Port au Prince, in order to supply the plants and make them more productive in respect of the environment.

See also :

https://www.haitilibre.com/en/news-9267-haiti-economy-lng-gas-terminal-official-launch-of-work.html

SL/ HaitiLibre



Twitter Facebook Rss
Send news to... Daily news...




Why HaitiLibre ? | Contact us | Français
Copyright © 2010 - 2026
Haitilibre.com